PART 1 – GENERAL

1.01 SUMMARY

A. This Section includes unglazed wirecut textured thin brick pavers for (interior) (exterior) building installation locations. Types of thin brick paver installations included are:
1. Thin brick pavers set in mortar beds with grouted joints.
2. Thin-set (dry set) installations with grouted joints

B. Related Sections:
1. Section 03300: Cast-in-Place Concrete (Use when pavers are installed over new monolithic slab floor or topping substrates).
2. Section 07900: Joint Sealers.

1.02 SUBMITTALS

A. Product Data: Submit manufacturer’s technical information and installation instructions for all materials specified.
B. Shop Drawings: Submit drawings indicating brick paver patterns and locations as well as locations of expansion and other joint types occurring in substrates.
C. Samples:
1. For initial selection purposes submit manufacturer’s color charts consisting of actual brick paver sections showing full range of colors, textures, patterns available for each type of paver indicated.
2. For verification purposes submit brick paver samples for each type, color and texture required, at least 12 inches square, mounted (in durable backing, and showing grout.
3. Submit full size samples of each type of trim and accessory unit for each required color.

D. Quality Assurance Control Submittals:
1. Qualification Data: Submit certification, as specified under Quality Assurance article, substantiating capabilities and experience of installing firms and installing workers.

1.03 QUALITY ASSURANCE

A. Single-source Responsibility:
1. Obtain each thin brick paver type, color, and finish from a single manufacturer and source with resources to provide products of consistent quality and appearance.
2. Obtain all setting and grouting materials from one manufacturer for each type required.

B. Installer Qualification: Install thin brick pavers using only experienced installers who have successfully completed paver installations with similar design, methods and materials.

C. Installation Standards: Provide installations complying with the following:
1. Tile Council of America (TCA) “Handbook for Ceramic Tile Installation”, latest edition.
2. ANSI A108.1 Installation of Ceramic Tile.

D. Preinstallation Conference: Prior to starting installations, conduct a conference at the Project site, with all involved parties in attendance to establish procedures, review schedules and submittals, and coordinate all installation requirements.

1.04 DELIVERY, STORAGE AND HANDLING

A. Deliver and store packaged materials in original packaging with seals unbroken and labels intact until time for use.

B. Prevent damage to materials, or contamination of setting and grouting materials, due to water, freezing, foreign matter, or other causes.

1.05 PROJECT CONDITIONS

A. Environmental: Set and grout pavers when ambient temperature in area is at least 50ºF and rising. Maintain ambient temperature for minimum 2 days prior to installation and 7 days after completion unless higher temperatures are required by referenced standards or material manufacturer’s instructions. Provide all precautionary measures necessary to ensure that excessive temperature changes do not occur.
2. Provide sufficient ventilation to allow installations to properly set.
3. Maintain adequate lighting levels in all installation areas.

B. Protective Penetrating Sealer: FBC recommends, prior to grouting, a protective penetrating sealer coat be applied to exposed tile surfaces to prevent adherence of grouting residue on exposed surfaces, and to protect from staining during construction period. If sealer is applied, provide protective measures to ensure sealer does not get onto bonding surfaces (back and edges) of tile. Inspect each tile prior to setting, and remove all traces of sealer from back and edges to ensure proper bond.

1.06 EXTRA MATERIALS

A. Furnish extra materials, that match product, installed, packaged with protective covering and identified with labels clearly describing contents,

B. Provide full size, undamaged pavers and trim in quantities equal to (2) (3) (5) ( ) percent of amount installed, for each type, color, and size.
PART 2 – PRODUCTS
2.01 THIN BRICK PAVER MATERIAL

A. Thin Brick Pavers: Sunshine Pavers as manufactured by FBC – Florida Brick and Clay Company, Inc., 1708 Turkey Creek Road, Plant City, Florida 33567 (813) 754-1521

B. Provide thin brick pavers complying with ANSI C902, “Pedestrian Light Traffic Paving Brick”, Standard Grade, unless otherwise indicated.
1. Thin brick pavers to be extruded unglazed, wire cut, with integral color through the entire paver body.
2. Brick Design Style: (Antique Pavers) (Flashed Pavers) (Teakwood Pavers) (Industrial Pavers) (Sunshine Pavers).
3. Paver size / thickness: {Standard size 7 5/8 inches x 3 518 inches x 1/2 inch (19.4 cm x 9.2 cm x 1.3 cm)) {Special order size 8 inches x 8 inches x 112 inch (20.3 cm x 20.3 cm x 1.3 cm)} {Industrial Paver size 7 5/8 inches x 3 5/8 inches x 1 inch (19.4 cm x 9.2 cm x 2.54 cm)).
4. Paver color: (insert color if known) or (to be selected from manufacturer’s standard array of colors and textures).

C. Trim Shapes: Provide paver trim and accessories, for indicated conditions, that match color and finish of adjoining flat pavers.

2.02 SETTING MATERIALS

A. Refer to latest edition of Tile Council of America (TCA) “Handbook for Ceramic Tile Installation”, with modifications for West Coast installations by Ceramic Tile Institute, “Installations and Performance Levels”, as a guide to determine method of setting brick paver work.

***REFER TO TCA HANDBOOK TO SELECT A PPROPRIATE SETTING MATERIALS LISTED IN B, C, D, AND E, BELOW. ALSO REFER TO TCA HANDBOOK FOR EPOXY, FURAN AND 0THER INSTALLATION METHODS AND MATERIALS.***

B. Materials for Portland Cement Mortar Setting Bed Installation Method:
1. Portland Cement: ASTM C150, Type 1.
2. Sand: ASTM C144.
3. Water: Potable.

***USE 4 AND 5 BELOW WHEN REQUIRED BY INSTALLAT70N METHODS RECOMMENDED BY TCA HANDBOOK.***

4. Reinforcing: ASTM A185; Size – 2 inch x 2 inch x 16/16 gauge welded wire mesh or equivalent.
5. Cleavage membrane: (ASTM D226, Type 1; 15 lb. asphalt saturated organic felt) (ASTM D 4397, polyethylene sheeting, minimum 4 mil thickness) or equivalent.

***NOTE: CLEAVAGE MEMBRANE MAY BE OMITTED IF WATERPROOF MEMBRANE AND PAN IS USED AND SPECIFIED ELSEWHERE. REFER TO WATERPROOFING MANUFACTURER’S SPECIFICATIONS FOR SUITABILITY AND LIMITATIONS APPROPRIATE TO SPECIFIC PROJECTS***

C. Materials for Thin Set (Dry-set) Portland Cement Mortar Installation Method:
1. Comply with ANSI A118.1, factory sanded
D. Materials for Thin Set Organic Adhesive Installation Method (interior use only):
1. Comply with ANSI A136. 1, Type I: Use or showers, tub recesses, and other areas requiring prolonged water resistance.
2. Comply with ANSI A 136.1, Type II: Use for all other installations not listed above, unless otherwise indicated.
E. Materials for Thin Set Latex-Portland Cement Mortar Installation Method:
1. Comply with ANSI A118.4.

2.03 GROUTING MATERIALS

***REFER TO TCA HANDBOOK TO SELECT GROUTING A MATERIALS LS LISTED IN A, B, OR C BELOW ALSO REFER TO TCA HANDBOOK FOR RECOMMENDATIONS FOR EPOXY, FURAN AND OTHER GROUTING METHODS AND MATERIALS.***
A. Materials for Commercial Portland Cement Grout Installations:
1. Comply with ANSI Al18.6 and formulate for the type of tile installed.
2. Color: As selected by Architect.
B. Materials for Thin Set (Dry-set) Grout Installations:
1. Comply with ANSI A118.6 and formulate for the type of tile installed.
2. Color: As selected by Architect.

C. Materials for Thin Set Latex-Portland Cement Grout Installations:
1. Comply with ANSI A118.6 and formulate for the type of tile installed.
2. Color: As selected by Architect.

2.04 ACCESSORY AND MISCELLANEOUS MATERIALS

A. Protective Penetrating Sealer: Natural Clay Products, Penetrating Sealer by Florida Brick and Clay Co.
B. Sealants: Provide sealants for joints as in Section 07900 for required use, Type, Grade and Class.

2.05 MIXES FOR MORTAR AND GROUT

A. Provide mixes for mortar and grout that comply strictly with proportioning, equipment, and other requirements of referenced standards and material manufacturer’s written product data.

PART 3 – EXECUTION

3.01 EXAMINATION

A. Examine areas and substrates that will receive setting materials, thin brick pavers, and trim before installation begins. With installers present, review for compliance with requirements for installation tolerances and other conditions that will affect performance of tile installation.

B. Acceptable Tolerances: Comply with tolerances as listed in latest edition of Tile Council of America (TCA) “Handbook for Ceramic Tile Installation” for installation condition and method.

C. Verify conditions and surfaces to receive thin brick pavers to ensure:
1. Surfaces are firm, dry, clean, and free of dust and oily or waxy films.
2. Grounds, anchors, plugs, recess frames, waterproof membrane, electrical and mechanical work in brick paver locations have been installed prior to start of paver work.
D. Do not proceed with work until defects or conditions adversely affecting quality and execution brick paver work are corrected.

3.02 PREPARATION

A. Lay0ut: Prepare layout of brick paver work so as to align joints of floor, base, and trim when pieces are of same size. Lay out SO as to center paver fields in both directions in each space or area, to minimize paver cutting, and provide joints of uniform widths. Provide lay out so as to minimize use of pavers that are less than one-half paver in size.
1. Locate expansion joints and other joint types to be sealant filled during installation of setting material. Do not saw cut joints after pavers have been installed.
2. Locate joints in paver surfaces directly over joints that occur in concrete or other substrate material.

B. Protective Penetrating Sealer: Protect exposed surfaces of paver against adherence of mortar and grout by applying a coating of specified discoloring clear resin penetrating type sealer at the Project site. Provide care so as not to get any sealer on back and edges of pavers.

3.03 INSTALLATION

A. ANSI Standard- Provide installations that comply with ANSI A108 series for paver installations applicable to type of setting and grouting required by Project.
B. TCA Guidelines- Provide installations that comply with TCA “Handbook for Ceramic Tile Installation” for methods and materials required by Project.
C. When waterproofing is required by Project conditions, do not install pavers until waterproofing material has cured and has been tested for watertightness.
D. Do not use pavers with chips, discoloration, voids or other defects that will be visible in finished work.
E. Locate expansion and other joints as specified above under Preparation, and at spacings and locations recommended in TCA Handbook
F. Install pavers in grid pattern unless otherwise indicated. Install pavers to comply with layout requirements specified in Preparation above.
G. Set and grout pavers in compliance with specified reference standards using specified materials. Install pavers to comply with the following TCA Installation Method(s):
1. TCA Method: ( ……………)

***REFER TO TCA HANDBOOK AND INSERT SELECTED INSTALLATION METHOD NUMBER APPROPRIATE TO PROJECT CONDITION. IF MORE THAN ONE METHOD IS REQUIRED, INDICATE LOCATION OF EACH TYPE ON DRAWINGS OR IN SCHEDULE***

H. Install trim at conditions and locations indicated.
1. Fill all expansion joints and other penetrations with specified sealants.

3.04 CLEANING AND PROTECTION

A. Upon completion of grouting, clean all paver surfaces to ensure they are free of all foreign matter.
1. Remove haze (residue) on pavers resulting from latex-portland cement grouting as soon as possible.

B. Do not clean pavers with acid solutions or chemical cleaners unless in accordance with both paver and grout manufacturer’s written recommendations.
1. Flush with clean water before and after cleaning.

C. Leave installations finished, clean, and free of chipped, broken, cracked, loose or other defective paver work.
D. Apply a surface coating of thin brick paver manufacturer’s recommended cleaner to enhance natural color of paver to achieve a high sheen or glossy appearance on the surface, apply paver manufacturer’s recommended top coat sealer with heavy acrylic solid or wax.
E. Apply a protective coat of manufacturer’s recommended neutral protective cleaner to completed paver work.
F. Protect exterior paver installations by applying a second coating of paver manufacturer’s recommended penetrating sealer, after grout his cured.
1. Refer to FBC published maintenance guide for Sunshine Pavers installation for additional details.

***OMIT ABOVE IF NO EXTERIOR INSTALLATIONS ON PROJECT. OMIT BELOW IF SECOND COAT IS NOT DESIRED FOR INTERIOR PAVERS.

G. Protect interior paver instillations by applying a second coating of paver manufacturer’s recommended penetrating sealer, after grout has cured.
H. Protect final paver installation in a manner, and so as to maintain conditions, to ensure paver work will not deteriorate or be damaged at time of Substantial Completion.
I. Cover entire paver floor area with a heavy-duty non-staining construction paper and tape in place.
J. Prohibit foot and wheeled traffic from newly paved area for a minimum of 7 days after grouting is completed.
K. Just prior to final acceptance, remove protective paper and rinse neutral cleaner from surfaces of pavers. Dry and lightly buff.
L. Refer to FBC published maintenance guide for Sunshine Pavers installation for additional details.